2015 Street Repair and Repaving Project

Pre project (NE Logan Street, 13th-14th)

Post project (NE Logan Street, 13th-14th)

The 2014 Transportation Bond included $5.2 million dollars for the rehabilitation and repaving portions of 84 City streets, totaling about 14 miles. The first phase of this work was completed in 2015.


The 2015 Street Repair and Repaving Project was completed in September of 2015 at a total project cost of $1,397,015. The work included the repair and repaving of 4.0 miles of City streets around the community. 182 curb ramps were updated as part of the project. The streets completed represent approximately 28.5% of repair and repaving work that will be completed as part of the bond funded improvements. The remaining work will occur over the next three summers (2016-2018).


Click here to view the project summary map, showing the locations of the 2015 projects.


Click here for information on the 2016 Street Repair and Repaving Project.